REGISTERED COMPANY NUMBER: RC000822 (England and Wales)
REGISTERED CHARITY NUMBER: 1124517
REPORT OF THE TRUSTEES AND
AUDITED FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31ST DECEMBER 2024
FOR
THE CHARTERED INSTITUTE OF PLUMBXNG &
HEATING ENGINEERING
clemen￿ Hoar Cummings
Chartered Accountants and Statutory Auditor
Riverside House
1-5 Como Street
Romford
Essex
RM7 7DN

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
CONTENTS OF THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31ST DECEMBER 2024
Page
Report of the Trustees
I to 14
Report of the Independent Audltors
IS to 17
statement of Flnanclal Activities
18
Balance Sheet
19 to 20
Cash Flow Statement
21
Notes to the Cash Flow Statement
22
Notes to the Flnancial Statements
23 to 33
Detalled Statement of Flnancial Actlvltles
33 to 35

COTrl¥P¢TENcE
AND
REPORT OF THE BOARD OF TRVSTEES
FOR THE PERIOD ENDING 31￿ DECEMBER 2024
Proud to be a Professional
Page I

THE CHARTERED INSTrruTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
The Trustees present their report with the financial statements of the charity for the year ending 31st
December 2024. The Trustees have adopted the provisions of the Statement of Recommended Practice
(SORP) 'Accounting and Reportino by Charities, issued in accordance with the Financial Reporting
standard for Smaller Entities effective 1st January 2019. In addition, Trustees have paid due regard to
the Charity Commission's guidance on public benefit in determining activities CIPHE Should undertake.
REFERENCE AND ADMINISTRATIVE DETAILS
Reglstered Company number
RC000822 (England and Wales)
Reglstered Charlty number
1124517
Registered offlce
Saxon House
27 Ouke Street
Chelmsford
CMI IHT
Trustees
P. Massey
N. Jones BA ACA
K. Mccallister EngTech MCIPHE RP
N. Overton MCIPHE
R. Mallender EngTech FCIPHE RP ceased 07.06.24
G. Westall EngTech MCIPHE RP
C. Brooks
M. Gumbs EngTech MCIPHE RP - appointed 07.06.24
Co-opted and Observer Speclalists to the Board of Trustees
P. Thom FCIPHE FRSA FCIM AIGFM
T. Morrison
date of resSgnation 18. 11.24
M. Bridges EngTech MCIPHE RP
H. Hung EngTech HonFCIPHE RP (Immediate Past President)
ceased 07.06.24
Honorary Company Secretarv
C. Brooks
President
Y. Orgil l appointed 07.06.24
A. Wildish CEng FCIPHE (Immediate Past President) - from 07.06.24
Chief Executlve Officer
Kevin Wellman EngTech FCIPHE RP
Auditors
Clemence Hoar Cummlngs
Chartered Accountants
Riverside House, 1 5 Como Street
Romford
Essex RM7 7DN
Solicitors
Penningtons Manches Cooper LLP
31 Chertsey Street
Guildford
Surrey GUI 4HD
Page 2

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
Bankers
Barclays Bank PLC
Knightsbridge Business Centre
PO Box 32014
London NWI 2ZG
Investment Advlsors
Cazenove Capital
Schroder Co. Limited
l London Wall Place
London EC2Y SAU
STRUCTURE, GOVERNANCE AND MANAGEMENT
Governlng document
The Chartered Inslitute of Plumblng and Heating Engineering is a company incorporated by Royal
Charteri granted on 12th February 2008. It is a registered charityi obtaining charitable status on 16 June
2008. The Institute Ss governed by its Royal Charter and Bye-Laws. The 8ye-Laws and Regulations are
under constant review and were last updated in 2017 and 2020 respectivelyi and future amendments will
be carried out when necessary.
Recruitment and appolntment of new Trustees
Applications for Trusteeship are sought by advertisement.
Induction and tralning of new Trustees
After appointment, an induction is arranged for new Trustees. Trustees serve up to a four-year period
and may be re-eletted for a further four-year period (effective from 2018). The Trustees meet at least
five times a year to review the strategy and performan￿ and to set the operatlng plans and budgets.
Organlsatlonal structure
There are committees covering membership, professional standards, technical servSces and investments.
The Chief Executive Officer is appolnted by the Trustees to manage the day-to-day operations of the
Institute.
Related partles
The Institute is the registered owner of 100% of the issued capital of Plumbing and Heating Promotions
Limited, which became dormant in 2022. The Institute is also the registered owner of IOOO/o of the issued
share capital of GreenPlumb Limited and SafePlumb Limited, which have remained dormant since thelr
respective incorporation.
Rlsk management
The Trustees have introduced a formal risk management process to assess business rlsks and implement
risk management strategies. The Trustees are pleased to report that the charity's internal financial
controls, in particular, conform to guidelines issued by the Charity Commission. The Trustees are fully
cognisant of their responsibility to evaluate and manage business risk, which they classified as:
a. Governance and Management
b. Operational Risks
Financial Risk
d. Environmental and External Factors
Compliance
Other Risks not classifiable under the above headings.
The Executive team discuss and rate business rlsks as they are identified. On-golng monitoring and
updates on risk management are undertaken through reports provided by the Chief Executive Officer.
Page 3

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
OBJECTIVES
The Purpose of the CIPHE is to enhance the safety, health and wellbeing of the public through a strong
qualified membership reinforced by their competency and technical expertise.
The Mission of the CIPHE is to operate as an independent technical and professional focal point and be a
catalyst for the plumbing and heating industry by providing technical and professional standards,
expertise, education and technical innovation to the operatives within its scope.
The Vlslon of the CIPHE is to create technical excellence through whlch the public will recelve the benefit
of a protected environment and enhanced sustainability together with improved safety and health
through the provislon of correctly installed, commissioned, malntained and decommlssioned plumbing
and heating systems.
The aims of the CIPHE are summarlsed in four areas in the following graphlc..
UBLIC
ALTh
EOUCATIONk
, RESEARCH
Strateglc Plan
The Strategic Plan Is fully reviewed each year. The Board approved the 2025 - 27 Strategic Plan, whlch
continues to focus on a number of the key activities In support of its role as the Chartered body for the
plumbing and heatlng industry.
Our strategy focusses on harnessing the considerable expertise available within the CIPHE, our
membership and our Industry colleagues. Together we work to promote best practice, create training
opportunities, and enhance education within the plumbing and heating industry.
To further safeguard public interest, especially for the vulnerable, and encourage safety withSn all
bulldings, an object of the CIPHE is to double membership whlch ultimately will lead to a safer
environment and help to outlaw rogue installers. The Strategic Plan is underpinned by a manSfesto
summarising key activities which is promoted to government, consumers and the industry.
The CIPHE'S prime aim is to advance for the benefit of the public the science, practice and principles of
plumbing and heating engineering and in exercising its responsibilities to satisfy the requirements of the
Charity Commission. It fulfils its objectives through several activities. A summary of these and key
achievements follows:
ACTIVITIES AND ACHIEVEMENTS
Publlc Benefit
Public benefit is derived from the activities set out below particularly in raising the safetyi health and
environmental aspects of plumbing and heating engineering in the perception of the public.
Page 4

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
Consumer Su
ort
The Institute continues to provide support to members of the public through telephone enqulrles and
through publication of articles in consumer magazines. In addition, it promotes the Find a Professional
Ilsting which is available through the CIPHE website. In 2024 it was decided that the Institute would
develop a model that increased the number of businesses listing via the online business directory. It was
subsequently agreed that from 1st January 2025, there would be two types of listing available
the
long-standing paid for premium service (including further enhancements) and a further one that was
included wlthin the standard membership fee.
Bullding Safety Advisory Panel CIPHE continues to support the Bullding Safety Advlsory Panel (BSAP).
Thls was formerly Working Group 2 that was instlgated after the Grenfell Tower Fire. The Construction
Leadership Council (CLC) is championing and supporting the delivery of safe and high-quality buildings
for those who live and work in them.
En
ineerln
& Buildin
Services Skllls Authorit
EBSSA
CLPHE is pleased to be proactively involved with EBSSA which was convened by Actuate UK members
together with other leading Sector bodies, such as BEAMA, TICA and the standards organisation MCS, to
provide a credible authorltalive voice for skills across all engineerlng and building services.
The key objectives of thls coalition are to provide analysis based on transparent data on the sector skills
demand and supplyi and utilise this evidence to highlight needs, educate, influence policy makers and
providers to close the skills shortage gaps with measurable interventions.
EBSSA is involved in the Constnjctlon Leadetship Councll's Skills Worklng Group 2, part of wider industry
and government efforts to 'raise the bar. on individual competence within the built environment In Ilne
with the new post-Grenfell competence regime established by the Bullding Safety Act.
cadem
ofEn
Ineerin
RAEn
CIPHE continues to support the RAEng and regularly promotes the need for improvements in education
and liceiising, Support was given to the report: 'Engineering a resilient and prosperous future, which
addressed policy priorities for the next UK parliament. RAEng hosts meeting with Professlonal
Engineering Institutes and the Engineering Council (EC). At the PEC meeting in November the EC
announced that it was considering a revlew of the 2012 statement on the status of engineers. It plans to
gather views on the potential future of regulatory approach, in the light of expected increased focus on
publlc trust and the need to have the right mechanisms to demonstrate both technical competence and
professional commitment. The CIPHE has been campaignlng for thi5 for many decades.
Gov
ment En
ment
CTPHE enjoyed a much increased engagement with numerous government department5 Includingi IfATE,
DESNZ, the Buildin¢J Safety Regulator and Defra.
DESNZ responded to the feedback on the'Increa5ing Boiler Efficiency Standards consultation, whlch
CIPHE responded to. It was encouraging to see that the department is wanting to mandate training for
low temperature systems. CIPHE'S qualification which 15 regulated by OFQUAL has seen over 2,000
individua15 attend the low temperature training since its launch two years ago.
Defra invited CIPHE to numerous round table events as well one to one meetings. Early in the year Defra
offlcials raised concerns about the current plumbing apprenticeship. It also a nnounced that It would be
introducing a Mandatory W6ter Labelling Efficlency Scheme In 2025.
Net Zero
Following the government's response to the Improving Boiler Efficiency Standards consultation, the
CIPHE wrote to DESNZ seeking clarification as to when the Low Temperature Qualification will be
mandated.
The CIPHE produced a Home Heating Guide, which explains the various New Zero technologies Sn Further
detail. It was made available to publlc and industry alike through the website. It has been reproduced
and promoted by Truslmark at their events and exhibitions.
The Institute continues to encourage the government to introduce licensing and ma ndatory training to all
involved wSth plumblng and net zero activities.
Page 5

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
lumbin
renticeshi
The DfE raised concerns with IfATE regarding the low completion rates for the current apprenticeship.
CIPHE was approached to investigate further and report back. An Education Survey was circulated widely
and found that 90010 of respondents were supportive of a proposal to develop both Level 2 and Level 3
apprenticeships. Some 360 responses from members and non-members were received. A Plumbing
Employers, Group was established which attrarted support from over 30 employers. They developed
proposals to apply to IfATE to develop a Level 2 and Level 3 apprenticeship. The submission that was
made to IfATE's Route Panel was extensive and was 5UPPOrted by many messages of support from
employers, a heating manufacturer, industry associations and independent training providers. It was
encouraging to see a comprehensive leller from Defra in full support of the new apprenticeshlp.
The interview with IfATE's Route Panel took place in December and during the first week of 2025, written
confirmation was received advising that CIPHE through its Plumbing Employers, Group should develop the
Standards for Level 2 and Level 3.
Re
ister of Plumbers - Public Re
Ister
The Worshipful Company of Plu mbers established the Register, which glves the publlc access to qualified
plumbers, in 1886. It helps protect public health and safety and promote5 the competence and conduct
of good plumbers.
In 1909, the Company handed over day-to-day management of its Reglster to the National Council for
the Registration of Plumbers, which, in 1953, was renamed the Registered Plumbers Association.
When the Association amalgamated with the Institute of Plumbing in 1970, the Worshipful Company
relinquished the Register and award of the designation "Registered Plumber" to the new Institute.
As at 31st December 2024, 70,403 Individuals had been entered onto the Register.
The Reglster of Plumbers Is maintained In the Membership Department and is avallable for inspection by
any member of the public by appointment.
RAister of Hea
Since its launch in January 2010, 880 members have been entered on to the Register of Heatlng
Professionals.
atersafe - Public Re
ister
The CIPHE continued its involvement wlth Watersafe whose objectives are to contribute to the safely of
drii)king water supplies and protection of customers, by:
Bringing together six Approved Contractors, Schemes.
Promotlng good plumbing practice and Complian￿ with the Water Supply {Water Fittings) Regulatlons
and Scottish Water Byelaws.
Providing easy access to online search facility listing approved and competent plu mblng businesses.
Reducing the rlsk to drinking water supplies from poor plumbing practice
The number of Watersafe registered members of CIPHE Increased by 20Wo from 331 to 396 in 2024,
8.80/0 of a total of 4,510 Approved Plumbers registered with the scheme.
Watersafe contrtbutes towards public health by helping consumers to protect their drinklng water and
avoid rogue traders by offeri ng them an accessible online directory of qualified plumbers.
Which? Trusted Trader
CIPHE continues to collaborate with Which? Trusted Trader to promote positive consumer facing
messaging regarding the plumbing and heating industry and provides a platform for them to
communicate wlth members through the membership benefits and services guide and resources. In
2024, this has included developing a CIPHE membership offer for members of the Which? Trusted Trader
scheme.
Page 6

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
CIPHE Manifesto
The manifesto continues to be published on an annual basis. It was distrlbuted widely during the year
and continues to be received favourably, especially by the trade press.
Covering key issues such as the health, safety and welfare of the public, the environment, edLJCation,
regulation and licencingi the CIPHE'S manifesto sits the plumbing and heating industry at the centre of
many key areas of Government policyi such as health, education, housing, energy and the environment.
An updated manifesto, including focused priority items for 2025 - 2027 was launched in December.
Su
ortin
Consumers throu
htheRe
istration Authorit
The Institute has a duty to investigate complaints that allege a member has not complied with the Code of
Professional Standards to act professionally, competently and responsibly. Upon notification of such
complaints, the complalnant is required to complete a form, whlch is then submitted to the Investigation
Panel (IP) to proceed further. During 2024, the Panel investigated 5 complaints, referring 2 to the
Disclpllnaiy Committee.
The Disciplinary Committee Impose sanctions on members when a complaint against them has been
upheld. During 2024, 1 member was removed from membership for falling to adhere to the Code of
Professlonal Standards
Educatlon
I Pathwa
A new career pathway flowchart has been produced by the CIPHE which details each route a learner
might lake across domestic plumbing and heating as well as commercial and Industrial.
The Approved Training Centres increased to 74 during the year.
ducational Develo
ment throu
h Competition
The CIPHE continues to support and engage with competitlons. Heating Installer Plumber of the Year
(HIPLOY) and a new all-Female Skills competition attract a wide audlence across England. Jerry Whitcley
(Technical Manager) is the Head Judge for both competitions which are valued by education,
manufacturers and industry bodies. It provldes access to a younger audience and capitalises their
knowledge of the CIPHE and what it stands for. We also support the Heating Installer of the Year Awards
that hold a review and celebrate best practice for existing installers. Thls Is celebrated at the largest
plumbing and heating show In June each year at the NEC Lnstallershow. During the Show we are also
prlvlleged to support and judge the Installer Merit Awards for seNices people do out of kindness.
Latterly, we were also asked to judge the PHAM News Energy Efficiency Awards held in London for thelr
successes in designing energy efficient heating and hot water systems across the UK.
The range of competitions we support has grown, to now include the HPM maga2ine. The success of the
HIPLOY competition and the Female Skills competitions bring many ways of engagements. Training
providers and their learners, manufacturer5 all seek the CIPHE services.
Langley College have used our service for training learners on Water Regulations and G 3 hot water
systems. These courses are part of the prerequisites for accessing green technologies,
One other new service provided is a Deep Dive quality checks for FE providers. Quallty of teaching and
learning and the student experience Is a vital quality check, we provided an independent servlce for the
LOW College who wlll use this to improve dellvery of plumbing and heating learnSng.
Buildin
Services En
ineerin
lo er Indust Board
CIPHE were invited by City & Guilds to partake in the Building Services Engineering Employer Industry
Board along with industry experts and employers to ensure the skills employers need are met for a more
productive workforce. Our representation 15 through the Employer Industry Board (EIB) which forms
part of thls group.
Page 7

THE CHARTERED INSTrfuTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
The EIB comprSses of employers, professional bodies and other sector organisations who collaborate to
ensure that educational services are fit for purpose.
New T Levels have been launched and are currently being trialled across the country. New criteria for
work experience have now been applied as well as funding for employers.
The contract for the T Levels has changed hands from City and Guilds to EAL/Wjec. They are revlsing the
structure of the pathways by combining plumbing and heating as one. Retention of learners has been an
issue, and the restructuring Is part of their solution. The Technical team has been invlted to review
content and to ensure mapping will meet the proposed changes of the apprenticeship.
Continuin
Professional Develo
ment and Academ
A requirement of the Code of Professional Standards is that members should undertake CPD to broaden
and maintain thelr knowledge and the CIPHE recommends that members should undertake 30 hours of
CPD on an annual basis. The Institute delivers many ways by which members can earn CPD hours,
including via CPD articles In P&H Engineering magazine.
The CIPHE Academy attrarted 493 registered users and 241 completed courses, wlth a further 93 courses
In progress by year-end.
Number of
Numberof
Nwnberof
Numborof
In progress
241
To assist wlth monitoring CPD, the CIPHE supports mycareerpath@, which is an online professional
development system, designed by the Engineering Council and adopted by many professional engineering
institutions for use by their members.
The CIPHE digital project Is Incorporating techtalk@ and smarttalk@ content, providing informed
technical and professional education and traSning across a range of subjects. The video content has
collectively had more than 70,000 views to date. The CIPHE Plumbing Engineering Service5 Design Guide
has been made freely available online for members and work to update the Guide section by section
continues.
A website for the member magazine, P&H Engineeringi is a￿SSIble at www.pandhengineering.co.uk.
Page 8

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
roved Trainin
Centre
The CIPHE has continued to promote its revised Approved Training Centre model that Includes
membership for the trainers and access to digital training tools that have been deve loped too.
The following colleges joined the Institute as Approved Training Centres (ATC) in 2024:
An91ia Tralning Centre @ College of West Anglia
Blackburn College
Ideal Heating Expert Academy - Hull
Ideal Heating Expert Academy - Leeds
Ideal Heating Expert Academy - Luton
North Shropshire College
South West Construction Academy Ltd
Walsall Training Centre Ltd
Wigan & Leigh College
Industry Engagement
World Plumbin
Council
The World Plumbing Council (WPC) signed a Memorandum of Understandlng (MOU) with Worldskills
International. This agreement marks a major milestone, celebrating 20 years of collaboration between
the organi5ations. We commend Ruben Duggan for achieving Silver medal at the 47th Worldskills
Competition that was held in Lyon, France.
The WPC sought applications for its three annual scholarships:
Two Education and Training Scholarships for indlvlduals actively involved in their local plumbing Industry:
These scholarships allow professionals to travel internationally and gain new insights into the Industry.
One United Association Instructor Training Program Scholarshlp: This scholarship enables a tralner,
Instructor or teacher from the plumbing industry to attend the annual United Association Instructor
Training Program In Ann Arbor, Michigan, USA.
The CEO updated the WPC Executive Board on progress for the WPC Conference in June 2026 In
collaboration with the TnstallerSHOW. The logo was launched at the 2024 1nstallerSHOW to great
acclaim.
Lord Ma
or Lecture
The CEO was invited by the 695tli Lord Mayor of London to carry out a virtual lecture as part of the
Gresham Society Lecture Series. The presentation on behalf of the Worshipful Company of Plumbers was
entitled 'The Need for Green Plumbing, UK & Worldwide..
Construction Industr
Council
CIPHE contlnues to support the CIC which Is an umbrella body for the Built Environment professions With
35 Members and 20 Associate members collectively representing over 500,000 people and several
thousand buslnesses. During the year the CIC has engaged with industry and government departments
rcgardlng numerous issues including: Invest 2035.. the UK'S modern industrial strategy, Golden Thread
guidance, Buildlng A Safer, Healthler And More Sustainable Future For All and Manifestos from the Built
Environment.
Industrial Associates
CIPHE continues to partner on projecls with some of the Industrlal Associates Development Group
ranging from support for apprenliceships and training to product focused CPD, the low carbon agenda,
and shared prioritie5 on matters of public safetyi wellbeing and the plumbing and heating industry
workforce. Regular Industrial Associate focused communications are included amongst the rest of our
output to members. Feedback from Industrial Associates highlight5 their support for CIPHE key messages
such as the manifesto. Issues around the aging workforce, current and future skills-gap, professional
routes into the industry and what this will mean for their businesses and their product5 continue to be a
priority and provide opportunities for CIPHE to highlight them. During a meeting hosted by Fernox in
November Industrial Associates were given an insight into the 3D technical projert they had kindly
sponsored depicting a resldential household plumbing and underfloor heating system. It will be launched
to colleges and training centres in January,
Page 9

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
RESEARCH & TECHNICAL
Technlcal Strategy Group
The Technical Strategy Group (TSG) operates as an independent technical and professional focal point
and aims to be an authority to the plumbing and heating industry by providing technical standards,
guidance, expertise and education & technical innovation. It achieves this through the appointment of
Technical Working Groups. the following Groups have been established: Water Safely; Heatlngi
Controls, Hot and Cold Water Services and Above & Below Ground Drainage. In addition to this, the
CIPHE have engaged in a wide variety of technical industry group meetings ensuring both the installer
and consumer are being represented correclly. This included revisions to the building regulations and
other matters associated with bolh water safety and the future of heat in buildings. In addition, work
commenced on carrying out revisions to the Plumbing Engineering Services Design Guide.
The PESDG Heatlng Section Is currently under Internal review by Paul Harmer and Mike Maskrey after
being externally reviewed by a number of industry experts. Parts I to 4 have currently been completed,
with work continuing via regular meetings.
MEMBERSHIP & PROMOTION
Membershlp and Englneerlng Councll
The total membership as at 31st December 2023 was 7,483, an Increase of 4% year-on-year.
Membership breakdown by category (Dec 2024)
FCIPHE
rain•a
22Tr)
IA Supporter
Api)roved T1￿￿ni
Leiilro
Iqii
j A'li.late
mpiinion
116
MLIPHE
561
ACIPHE
At the end of 2024, ACIPHE, MCIPHE and FCIPHE together totalled 730kn of CIPHE membership
Page 10

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
Appllcatlon breakdown by category 2024
IA oUPPOrter
FCIPHE
Ogb
Approved r8irir
¢.ftntr
1gb
T'alnee
41%
MCIPHE
Companion
116
Afliliatg
29)
ACIPHE
| 84
Throughout 2024, ACIPHE, MCIPHE and FCIPHE totalled 53% of membershlp applicatlons received
During 2024, 8 appllcants were newly reglstered at EngTech level, l at IEng level and O at CEng level.
As at the end of 2024, the Institute had 652 Englneering Technicians, 67 Incorporated Engineers and 25
Chartered Engineers.
Master Plumber Certificate
On Monday Ilth March 2024, the Master Certificate Awards for Construction Liveries were held at the
Egyptian Hall, Mansion House hosted by Lord Mayor Alderman Professor Michael Mainelli. Nigel Baldwin
EngTech FCIPHE RP and Adrian Paul Liddell EngTech MCIPHE RP RHP were presented wlth their Master
Plumber Certificates.
Plumbing Professionals Development Scheme
In January 2024, The CIPHE and Worshipful Company of Plumbers launched its Plumbing Professionals
Development Scheme having identified 10 talented individuals to support in the early stages of their
careers. Through the year, thi5 has included providing additional learning opportunities and experiences,
networking and support via a mentoring programme and encouragement and guidance to achieve
advanced stages of professional registration and recognition. The scheme continues into 2025 with a new
cohort of beneficiaries identified.
Page 11

THE CHARTERED INSTITIJTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
Exhibitions
The CIPHE was again a key partner and exhibitor at the InstallerSHOW in its new home at the
Birmingham NEC. Once again, CIPHE partnered with a number of Industrial Associate members to run a
competition that meant CIPHE was vlsible to help drive footfall across a number of stands The Institute
asslsted and contributed to presentations at the event, the promotion of a Certlficate of Excellence
conjunction with the Worshipful Company of Plumbers and with judging for the Enstaller Merit Awards and
the Heating Installer of the Year Award. Overall, the event was another great success for the CIPHE,
generating new members, strengthening ties with existing members.
Promotlonal Campaigns and Medla
The CIPHE has worked closely with the plumbing and heating trade press, who con515tently assisted in
promoting the CIPHE key messages. CIPHE, via its staff and its members, has also been increasingly
prominent in national media regarding plumbing and heating issues, including an appearance on This
Morningi and an extensive consumer focused advisory piece in Grand Designs magazine.
The CIPHE continues its calls for greater levels of communication between government and organisations
such as the CIPHE to establish long-term strategies which will combat the fuel poverty epldemlc. The
CIPHE and its membership is dedicated to safeguarding the most vulnerable in socletyi and that include5
those Ilving in fuel poverty. With continued volatility surrounding fuel prices there Is increasing concern
that many more people wlll enter into fuel poverty. The Government must seek to protect these people;
only by working together can we stop the unnecessary and highly preventable deaths aitributable to thls
Issue.
Website statistlc$
CIPHE web traffic has declined compared to 2023, but the number of pages vlsited and average length of
time spent on the website have both increased:
Slte users: 51,226
Sessions: 78,390
Sessions per user: 1.53
Page views,. 260,217
Pages per session: 5.08
Average engagement time per user: 02:26
In addition, during 2024, the followlng transactions took place through the website:
352 people joined online - total value of £63,697
830 shop orders placed total value of £29,762
1,922 membership renewal payments made online - total value of £302,422
Soclal Media
The CIPHF is active on social media. In 2024, we decided to de-prioritise the use of X (formerly known as
Twitter) and instead focus attention on Instagram instead. By the year-end, our followers across our
priority channels had increased as follows:
Lin kedln
Facebook
Instag ram
6,058 {13Wo increase)
3,091 {20/0 increase)
713 (started year at o)
Annual General Meetlng
The 16th AGM of CIPHE was held on Friday 7th June. The AGM was held at Macdonald Alveston Manor
Hotel & Spa In Stratford-Upon-Avon and was also conducted via Zoom Conference Facilities. In excess of
51 members participated worldwide to see Yvonne Orgill take office as National President and Jason Clark
as Vice-President. Melville Gumb5 was elected as Voting Member Trustee to serve on the Board for 4
years.
Page 12

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
FINANCIAL REVIEW
Reserves pollcy
The Ti-ustees regularly review the reserves of the charity to meet its financial commitments and achieve
its objectives. They consider that the charity had sufficient reserves to operate for the next 12 months
and into the foreseeable future.
The prime objective of the reserves policy of the Trustees is to maximise CIPHE surplus funds which are
held in a range of interest bearing bank accounts. In particular the General Fund is invested with due
regard to potential calls on the fund as identified in the Strategic Plan.
Investment pollcy and objectlves
The Institute has the power to make any Investment that the Trustees see flt.
Following the sale of the freehold property at 64 station Lane an Investment Committee was formed and
Cazenove were appointed as the CIPHE investment advisors. The property sale proceeds have been part
Invested in a cautious portfolio fund ready for a purchase of a new freehold premises and part invested in
a longer term portfolio to maximise yields. The Investment objective is to produce the best investment
return within an acceptable level of risk.
Head Offlce
Ln June 2024 we relocated out of 64 Station Lane following Its sale, to a managed office in Saxon House,
Chelmsford as a temporary measure while we seek a more permanent residence.
ACKNOWLEDGEMENT
The CLPHE 2024 Trustee Report is structured around our key objectives and highlights key activitles
throughout the year. Acknowledgement and appreciation must be given to the Truslees, Presidents,
committee and working group representatives, volunteers, staff and industry stakeholders who have
assisted the CIPHE throughout the year.
Your commltment and enthuslasm In supporting our alms and activities has challenged, motlvated and
Insplred the CIPHE to progress and we look forward to worklng closely wlth you in the comlng years.
STATEMENT OF TRUSTEES RESPONSIBILITIES
The trustees (who are also the directors of The Chartered Institute of Plumbing & Heating Engineering for
the purposes of company law) are responsible for preparing the Report of the Trustees and the financlal
statements in accordance with applicable law and United Kingdom Accounting Standards (United Kingdom
Generally Accepted Accounting Practice) including Financial Reportlng Standard 102 "The Flnancial
Reporting Standard applicable in the UK and Republic of Ireland"
Company law requires the trustees to prepare financial statements for each flnanclal year which give a
true and falr view of the state of affairs of the charitable company and of the incoming resources and
application of resources, including the income and expenditure, of the charitable company for that period.
In preparing those financial statements, the trustees are required to
select suitable accountlng policies and then apply them consistently;
observe the methods and principles in the Charity SORP.
make judgements and estimates that are reasonable and prudent;
prepare the financial statements on the going concern basis unless It is inappropriate to presume that
the charitable company will continue in business.
The trustees are responsible for keeping proper accounting records which disclose with reasonable
accuracy at any time the financial position of the charitable company and to enable them to ensure that
the financial statements comply with the Companies Act 2006. They are also responsible for safeguarding
the assets of the charitable company and hence for taking reasonable steps for the prevention and
detection of fraud and other irregularities.
Page 13

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
REPORT OF THE TRUSTEES
FOR THE YEAR ENDED 31ST DECEMBER 2024
STATEMENT AS TO DISCLOSURE OF INFORMATION TO AUDITORS
In so far as the trustees are aware-
there is no relevant audit information of which the charitable company's auditors are
unaware. and
the trustees have taken all steps that they ought to have taken to make themselves aware of any
relevant audit information and to establish that the auditors are aware of that informatS0n.
AUDITORS
The auditors, Clemence Hoar Cummings, wlll be proposed for re-appointment at the forthcomlng Annual
General Meeting.
ON BEHALF OF THE BOARD OF TRUSTEES:
Approved by order of the board of trustees on
by:
.2610312025............. and slgned on its behalf
By order of the Board of Trustees
Paul Massey, Chairman
Date: 2610312025
Page 14

REPORT OF THE INDEPENDENT AUDITORS TO THE TRUSTEES OF
THE CHARTERED INsfITUTE OF PLUMBING &
HEATING ENGINEERING
Opinion
We have audited the financial statements of The Chartered Institute of Plumbing & Heating Engineering
(the 'charitable company,) for the year ended 31st ￿e￿mber 2024 which comprise the Statement of
Financial Activities, the Balance Sheet, the Cash Flow Statement and notes to the financial statements,
including a summary of significant accounting policies. The financial reporting framework that has been
applied in their preparation is applicable law and United Kingdom Accounting Standards (United Kingdom
Generally Accepted Accounting Practice), including Financial Reporting Standard 102 'The Financial
Reporting Standard appllcable in the UK and Republic of Ireland..
In our opinion the financial statements:
give a true and fair vlew of the state of the charitable company's affairs as at 31st December 2024 and
of its incomlng reSoUr￿S and application of resources, including its income and expenditure, for the
year then ended.
have been properly prepared in accordance with Unlted Kingdom Generally Accepted Accounting
Practice, including Financial Reporting Standard 102 'The Financial Reporting Standard applicable in
the UK and Republlc of Ireland,; and
have been prepared in accordance with the ￿ qulrements of the Companles Act 2006.
Basls for oplnlon
We conducted our audlt In accordance with International Standards on Auditing (UK) (ISAS (UK)) and
applicable law. Our responsibilities under those standards are further de.fcribed in the Auditors,
responsibilities for the audit of the financial statements section of our report. We are independent of the
charitable company in accordance with the ethical requirements that are relevant to our audit of the
financlal statements In the UK, including the FRC'S Ethical Standard, and the provisions available for
small entltles, in the circumstances set out In note 23 to the financial statements, and we have fulfilled
our other ethical responsibilities In accordance with these requirements, We believe that the audSt
evldence we have obtalned is sufficient and appropriate to provlde a basis for our opinion.
Conclusions relatlng to golng concern
In auditing the financial statements, we have concluded that the tnjstees, use of the going concern basis
of accounting in the preparation of the financlal statement5 Is appropriate.
Based on the work we have performed, we have not identifi'ed any material uncertaintles relatlng to
events or conditions that, individually or collectivelyi may cast slgnificant doubt on the charitable
company's ability to continue as a going concern for a period of at least twelve months from when the
financial statements are authorlsed for issue.
Our responsibilltles and the responsibilities of the trustees with respect to golng concern are described in
the relevant sections of thls report.
other Informatlon
The trustees are responslble for the other information. The other Information comprises the Information
Included in the Annual Report, other than the financial statements and our Report of the Independent
Auditors thereon.
Our opinion on the financial statements does not cover the other informatlon and, except to the extent
otherwise explicitly stated in our report, we do not express any form of assurance conclu51on thereon.
In connection with our audit of the financial statements, our responslbility is to read the other information
and, in doing so, consider whether the other information 15 materially inconsistent with the Financial
statement5 or our knowledge obtained in the audit or otherwise appears to be materially misstated. If we
Identify such materlal incon5islencies or apparent materiél misstatement5, we are requlred to determine
whether this gives rise to a material misstatement in the financial Statements themselves. If, based on
the work we have performed, we conclude that there is a material misstatement of this other
Information, we are required to report that fact. We have nothing to report in thi5 regard.
Page 15

REPORT OF THE INDEPENDENT AUDITORS TO THE TRUSTEES OF
THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
Matters on which we are required to report by exceptlon
We have nothing to report in respect of the following matters where the Charities (Accounts and Reports)
Regulations 2008 requires us to report to you if, in our opinion-
the information given in the Report of the Trustees is inconsistent in any material respect with the
financial statements. or
the charitable company has not kept adequate accounting records, or
the flnancial statements are not in agreement with the accounting records and returns. or
we have not received all the information and explanations we require for our audlt.
Responsibilitiès of trustees
As explained more fully in the Statement of Trustees, Responsiblllties, the trustees (who are also the
directors of the charitable company for the purposes of company law) are responsible for the preparation
of the financial statements and for being satisfied that they give a true and falr view, and for such
internal control as the trustees determlne is necessary to enable the preparation of ffinanclèl statement5
that are free from material misstatement, whether due to fraud or error.
In preparing the financlal statements, the trustees are responsible for assessing the charltable company's
ability to continue as a going concem, disclosingi as applicable, matters related to going concern and
using the going concern basis of accounting unless the trustees either intend to liquidate the charitable
company or to cease operations, or have no realistic alternative but to do so.
Our responslbllltles for the audlt of the financlal statements
We have been appointed as auditors under Section 144 of the Charities Act 2011 and report in
accordance with the Act and relevant regulations made or having effect thereunder.
Our objectives are to obtain ￿aSOnable assurance about whether the financial statements as a whole are
free from material misstatement, whether due to fraud or error, and to issue a Report of the Independent
Audltors that includes our oplnion. Reasonable assurance is a high level of assurance, but is not a
guarantee that an audit conducted in accordance wlth ISAS (UK) will always detect a material
misstatement when It exists. Misstatements can arise from fraud or error and are considered material if,
individually or in the aggregate, they could reasonably be expected to Influence the economic decislons of
user5 taken on the ba51s of these financial statements.
The extent to which our procedures are capable of detecting irregularities, Including fraud Is detalled
below:
Irregularities, including fraud, are instances of non-compliance with laws and regulJtlons. We design
procedures in Ilne with our responslbllities, outlined above, to detect material misslatements i n respect of
Irregularities, including fratjd. The extent to whlch our procedures are capable of detecting Irregularities,
includiiig fraud is detailed below:
We have designed our work to ensure thot laws and regulations have been adhered to, and the
transactions undertaken by the Charity ère properly reflected in the financial statements, We designed
procedures whlch included, but were not limited to:
Agreeing financlal statement disclosures to underlying supporting documentation.
Enquiring of management as to actual and polential litigation and claims.
We have obtained a detailed understanding of the Charity's intemal control systems and we have used
the knowledge <Jained to identify any areas of risk of mis-statement or fraud. To address the risk of fraud
through management bias and override of controls, we tested journal entrie5 to identify unusual
transactions. Making enquiries of management as to where they considered there was susceptibility to
fraud, thelr knowledge of actual, suspected, and alleged fraud.
Page 16

REPORT OF THE INDEPENDENT AUDITORS TO THE TRUSTEES OF
THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
We have evaluated the appmpriateness of accounting policie5 used and the reasonableness of accountlng
estimates and related disclosures made by the trustees.
We concluded on the appropriateness of the trustees. use of the going concern basis of accounting and,
based on the audit evidence obtained, whether a material uncertainty exists related to events or
conditions that may cast significant doubt on the charitable company's ability to continue as a going
concern. If we conclude that a material uncertainty exists, we are required to draw attention in our
auditor's report to the related disclosures in the financial statements or, if such disclosures are
inadequate, to modify our opinion. Our conclusions are based on the audit evidence obtained up to the
date of our auditor's report. However, future events or conditions may cause the charitable company to
cease to continue as a going concern.
We communlcate with those charged with governance regarding, among other matters, the planned
scope and timing of the audit and significant audit findings, including any significant deficlencles in
internal control that we Identify during our audit.
We have then designed our audit tests in each area to identify whether In respect of the transactlons we
have selected for testing the relevant controls have operated as expected. We plan our work specifically
to identify any areas where there Is a susceptibility to fraud such as understatement of subscription
Income, or material mls-statement such as understatement of subscriptions received in advance, then
design tests to mitigate this rlsk. Our work includes a proof In total based on the tlered subscription rates
of membershipi and ensuring that the appropriate revenue has been recogni5ed.
Because of the Inhe￿nt limltatlons of an audit, there is a risk that we will not detect all irregularities,
including those leading to a materlal mlsstatement in the financial statements or non-compliance with
regulation. This risk increases the more that compliance with a law or regulation is removed from the
events and transactions reflected in the financial statements, as we will be less likely to become aware of
Instances of non-compliance. The risk is also greater regarding irregularities occurring due to fraud rather
than error, as fraud Involves intentional concealment, forgery* collusion, omission or misrepresentation.
A further description of our responsibillties for the audit of the financial statements is located on the
Financial Reportin9 Council's website at www.frc.org.uk/auditor5responsibilities. This descrlptlon forms
part of our Report of the Independent Auditors.
Use of our report
This report is made solely to the charitable company's trustees, as a body, In accordance wlth Part 4 of
the Charities (Accounts and Reports) Regulallons 2008. Our audit work has been undertaken so that we
might state to the charltable company's trustees those matters we are required to state to them In an
auditors, report and for no other purpose. To the fullest extent permitted by law, we do not accept or
assume responsibility to anyone other than the charitable company and the charitable company's
trustees as a bodyi for our audit work, for this report, or for the opinions we have formed.
oi(0
Clemence Hoar Cummings
Chartered Accountants and Statutory Auditor
Ellgible to act as an auditor in temis of Section 1212 of the Companies Act 2006
Riverside House
1-5 Como Street
Romford
Essex
RM7 7DN
Date.. 26 March 2025
Page 17

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
STATEMENT OF FINANCIAL ACTIVITIES
FOR THE YEAR ENDED 31ST DECEMBER 2024
2024
Total
funds
2023
Total
funds
Unrestricted Restricted
funds
funds
Notes
INCOME AND ENDOWMENTS FROM
Charitable activities
EdL6catlona l Magazines & Directory
Mal ntalning Professional Standards &
Awareness
36,408
36,408
36,095
948,580
948,580
940,737
other tradlng activities
Investment income
other income
167,293
51,168
219 253
167,293
51,168
219 253
103,601
13,875
Total
1 422 702
1 422 702
1 094 308
EXPENDITURE ON
Raising funds
22,925
22,925
19,864
Charltable actlvlties
F.dur.ational M4yg(iiSnes & Directory
Support Servlces for Members
Maintalning Professlonal Standards &
Awareness
391,590
323,002
391,590
323,002
349,173
293,044
505 457
505 457
454 331
Total
1 242 974
1 242 974
1 116412
Net gains on Investments
NET INCOME/(EXPENDITURE)
Other recognised gains/(losses)
Gains on revaluation of flxed assets
187,611
187,611
(22,104)
310 000
Net movement in funds
187,611
187,611
287,896
RECONCILIATION OF FUNDS
Total funds brought forward
1,561,119
1,561,119
1,273,223
TOTAL FUNDS CARRIED FORWARD
1 748 730
1 748 730
1 561 119
The notes form part of these financial statements
Page 18

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
BALANCE SHEET
31ST DECEMBER 2024
2024
Total
funds
2023
Total
funds
Unrestricted
funds
Restricted
funds
Notes
FIXED ASSETS
Inlangible assets
Tangible assels
Investments
14
43,276
15
8,707
16 1 310 251
43,276
8,707
1 310 251
51,148
1,105,278
1,362,234
1,362,234
1,156,429
CURRENT ASSETS
stocks
Debtors
Cash at bank
17
18
6,018
76,260
650 145
6,018
76,260
650 145
8,633
61,005
684 573
732,423
732,423
754,211
CREDITORS
Amounts falling due withln one year
19 (345,927)
(345,927) (349,521)
NET CURRENT ASSETS
386 496
386 496
404 690
TOTAL ASSETS LESS CURRENT
LIABILITIES
1,748,730
1,748,730
1,561,119
NET ASSETS
1 748 730
1 748 730
1 561 119
FUNDS
Unrestricted funds:
General fund
Revaluation Reserve
21
1,740,847
528,134
1 032 985
1 748 730
1 561 119
TOTAL FUNDS
1 748 730
1 561 119
The charitable company is entltled to exemption from audit under Section 477 of the Companles Act 2006
for the year ended 31st December 2024.
The members have not deposited notice, pursuant to Sectlon 476 of the Companies Act 2006 requlrlng
an audit of these financial statements.
The trustees acknowled9e their ￿SponSibl11t1eS for
{a)
ensuring that the charitable company keeps accounknng records that comply with Sections 386 and
387 of the Companies Act 2006 and
(b) preparlng financial statements whith give a true and fair view of the state of affairs of the
charitable company as at the end of each financial year and of its surplus or deficit for each
financial year in accordance with the requirements of Sections 394 and 395 and which otherwise
comply with the requirements of the Companies Act 2006 relating to financial statements, so far
as applicable to the charitable company.
These financial statements have been audited under the requirements of Section 145 of the Charities Act
2011.
The notes form part of these financial statements
Page 19
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
BALANCE SHEET - continued
31ST DECEMBER 2024
These financial statements have been prepared in accordance with the provisions applicable to charitable
companies subject to the small companies regime.
The financial statements were approved by the Board of Trustees and authorised for issue on
and were signed on its behalf by:
N R Jones - Trustee
P Ma55ey - Trustee
The notes fom part of these financial statements
Page 20

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
CASH FLOW STATEMENT
FOR THE YEAR ENDED 31ST DECEMBER 2024
2024
2023
Notes
Cash flows from operatlng actlvities
Cash generated from operations
Interest paid
(25,822)
23 009)
40,654
16 072)
Net cash (used in)Iprovided by operating activities
48 831)
Cash flows from investing actlvltles
Purchase of inta ngible fixed assets
Purchase of tangible fixed assets
Purchase of fixed asset Investments
Sale of tangible flxed assets
Interest received
(46,296)
(7,357)
(1,302,365)
1,319,253
(15,525)
(5,598)
Net cash provided by/(used in) inve5tlng activities
Change In cash and cash
equivalents In the reporting perlod
Cash and cash equlvalents at the
beginnlng of the reporting perlod
(34,428)
17,334
684,573
667 239
Cash and cash equlvalents at the
end of the reporting perlod
650 145
684 573
The notes form part of these financial statements
Page 21

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE CASH FLOW STATEMENT
FOR THE YEAR ENDED 31ST DECEMBER 2024
RECONCILIATION OF NET INCOME/(EXPENDITURE) TO NET CASH FLOW FROM
OPERATING ACTIVITIES
2024
2023
Net Income/(expendlture) for the reporting perlod (as per
the Statement of Financral Actlvities)
Adjustments for:
Depreclation charges
Losses on investments
Profit on disposal of flxed assets
Inlerest received
Interest paid
Decrease/<increase) in stocks
Increase In debtors
(Decrease)/increase in creditors
187,611
(22,104)
58,096
(7,883)
(219,253)
(51,168)
23,009
2,615
(15,255)
51,986
(13,875)
16,072
(1,758)
(18,013)
Net cash (used in)/provlded by operatlons
25 822)
ANALYSIS OF CHANGES IN NET FUNDS
At 1.1.24
Cash flow At 31.12.24
Net cash
Cash at bank
684 573
34 428)
650 145
684 573
34 428)
650 145
Total
684 573
34 428)
650 145
The notes form part of these financial statements
Page 22

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS
FOR THE YEAR ENDED 31ST DECEMBER 2024
ACCOUNTING POLICIES
Basis of preparlng the financial statements
The flnancial statements of the charitable companyi which is a public benefit entity under FRS 102,
have been prepared in accordance with the Charities SORP (FRS 102) 'Accounting and Reporting
by Charities-. Statement of Recommended Practice applicable to charities preparing their accounts
in accordance with the Financial Reporting Standard applicable in the UK and Republic of Ireland
{FRS 102) (effective l January 2019),, Financial Reporting Standard 102 'The Flnancial Reporting
Standard applicable in the UK and Republic of Ireland, and the Companles Act 2006. The financial
statements have been prepared under the historical cost convention, with the exception of
investments which are included at market value, as modified by the revaluation of certain assets.
The servlces provided by the charity are detailed in the report of the Trustees in order to benefit
the general public.
Income
All Income is recognised in the Statement of Financial Activities once the charity has entitlement to
the funds, it is probable that the income will be received and the amou nt can be measured reliably.
the following specific policies are applied to particular calegories of income:
Donated servlces and facilities are Included at the value to the charlty where this can be
quantlfied, The value of services provided by volunteers has not been included in these accounts.
Investment income and membership fees are included when receivable. Subscriptions received
In advance are recognised as deferred Income.
Expenditure
Liabilities are recognised as expenditure as soon as there is a legal or constructive obligatlon
commlttlng the charity to that expenditure, it is probable that a transfer of economlc benefits will
be required In settlement and the amount of the obligation can be measured reliably. Expendlture
is accounted for on an accruals basis and has been classified under headings that aggregate all
cost related to the category. Where costs cannot be directly altributed to particular headSngs they
have been allocated to actlvlties on a basis consistent with the use of resources.
Grants offered subjett to conditions which have not been met at the year end date are noted as a
tt)mmitment but not accNed as expenditu￿.
Allocatlon and apportlonment of costs
Where costs cannot be directly attributed to partlcular headings they have been allocated to
activities on a basis consistent with the use of resources.
Intangible assets
Development costs are held at cost until the intangible asset is available for use.
Amortisation will be provided at the following annual rate in order to write off each asset over its
e5tlmated useful life.
Development costs at 2590 on cost
Tangible flxed assets
Freehold property is held at fair value. Any adjustments in fair value will show as a surplus or
deficit in the year.
Depreclation is provided at the following annual rate in order to write off each asset over its
estlmated useful life.
Fixtur'es and fittings at 25Qh on cost
Investments
The holding value5 of shares in subsidlary undertakings are ￿ported at historical cost.
Page 23
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
ACCOUNTING POLICIES - continued
stocks
stocks are valued at the lower of cost and net realisable value, after making due allowance for
obsolete and slow moving items.
Taxation
As a charityi The Chartered Institute of Plumbing and Heating Engineering Is exempt from tax on
income and galns falling within section 505 of the Taxes Act 1988 or s256 of the Taxation of
Chargeable Gains Act 1992 to the extent that these are applled to its charitable objects.
Fund accounting
Unrestrlcted fund5 can be used in accordan￿ with the charltable objectlves at the dlscretion of the
trustees.
Restricted funds can only be used for particular restricted purposes wlthin the objects of the
charity. Re5triclions arise when speclfied by the donor or when funds are ralsed for particular
restricted purposes.
Deslgnated funds are unrestricted funds 'ring fenced, by the trustees for parllcular purposes.
Further explanation of the nature and purpose of each fund Is included in Ihe notes to Ihe financial
statements.
Hlre purchase and leaslng commitments
Rentals pald under operating leases are charged to the Statement of Financlal Activitie5 on a
straight line basis over the period of the lease.
Pension costs and other post-retlrement beneflts
The charitable company operate.s a defined contribution pension scheme. Contributions payable
to the charitable company's pension scheme are charged to the Statement of Financlal Activities In
the period to which they relate.
OTHER TRADING ACTIVITIES
2024
2023
Sales of supplies
Office services
Sundry income
79,657
83,154
57,876
30,617
lJf 108
167 293
103 601
INVESTMENT INCOME
2024
2023
Deposit account interest
Page 24
contlnued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
INCOME FROM CHARITABLE ACTIVITIES
2024
2023
Activity
Educational Magazines & Directory
Maintaining Professional Standards &
Awareness
Publications
36,408
36,095
Fees from members
948 580
940 737
984 988
976 832
RAISING FUNDS
other tradlng activities
2024
2023
Cost of supplies sold
CHARITABLE ACTIVITIES COSTS
Grant
funding of
activities
(see note
7)
Support
costs (see
note 8)
Direct
Costs
Totals
Educational Magazines & Directory
Support Servlces for Members
Maintalnlng Professional Standards
& Awareness
301,121
90,469
297,006
391,590
323,002
25,996
223 027
282 430
505 457
524 148
669 905
1 220 049
GRANTS PAYABLE
2024
2023
Support Services for Members
SUPPORT COSTS
staff
costs
Commun
-Ications
Office
costs
Premises
costs
Educational Magazines &
Directory
Support Services for
Members
Maintalnlng Professional
Standards & Awareness
24,316
10,273
44,953
3,258
175,623
10,273
44,955
23,518
9,406
270 189
134 875
Page 25
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS- contlnued
FOR THE YEAR ENDED 31ST DECEMBER 2024
SUPPORT COSTS - continued
Meeting &
conference
expenses
Finance
costs
Governance
costs
other
Totals
Educational magazines &
Directory
Support Services for
Members
Maintaining Professional
standard5 & Awareness
7,669
90,469
7,669
9,243
14,814
10,911
297,006
282 430
669 905
Actlvity
Basis of allocation
Staff costs
Use of Staff Time
Communicatlons
Use of Resources
Office costs
Use of ReSoUr￿S
Premises costs
Use of Staff Time
Finance costs
Use of Resources
Other
Use of Resources
Meeting & conference expensesuse of Resources
Governance costs
Use of Resources
NET INCOME/(EXPENDITURE)
Net income/(expenditure) is stated after charying/{crediting):
2024
2023
Auditors, remuneration
Taxation compliance Servi￿S
Depreciation - owned assets
Other operating leases
Surplus on disposal of fixed assets
Development costs amorti5ation
10,897
1,085
3,928
24,036
(219,253)
10,058
1,045
4,459
10. TRUSTEES, REMUNERATION AND BENEFITS
There were no trustees, remunerallon or other benefits for the year ended 31st December 2024
nor for the year ended 31st December 2023.
Trustees, expenses
Reimbursed meeting and travel expenses totalling £1,923 (2023: £652 were paid to two of the
trustees during the year.
Expenditure related to the Presidents dinner event were £4,192 (2023: £4,432 ).
Page 26
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL sfATEMENTS- continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
11. STAFF COSTS
2024
2023
Wages and salaries
Social securily costs
Other pension costs
490,042
46,961
456,052
42,822
567 249
528 289
The full time equivalent number of employees for the year was as follows.
2024
2023
Membership
Technical
Support
Total
The average monthly number of employees during the year was as follows..
2024
2023
Management
Technical
Administratlon
li
li
The number of employees whose employee benefits (excluding employer pension costs) exceeded
£60,000 was:
2024
2023
£60,001- £70,000
£ioo,ooi £iio,000
Key Management personnel employee benefits are £172,107 (2023: £163,358 ).
12. HIGHER EARNING EMPLOYEES
Contributions totalllng £17,905 (2023: £17,019) paid during the year under money purchase
scheme for higher paid employees,
Page 27
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - continued
FOR THE YEAR ENDED 31st DECEMBER 2024
13. COMPARATIVES FOR THE STATEMENT OF FINANCIAL ACTIVITIES
Unrestricted
funds
Restricted
funds
Total
funds
INCOME AND ENDOWMENTS FROM
Charitable activitles
Educational Magazines & Direclory
Mdintalning Professional Standards &
Awareness
36,095
36,095
940,737
940,737
Other trading activities
Investment income
103,601
103,601
Total
1 094 308
1094 308
EXPENDITURE ON
Raising funds
19,864
19,864
Charltable actlvltles
Educational Magazlnes & Dlrectory
Support Services for Members
Maintaining Professional Standards &
Awareness
349,173
293,044
349,173
293,044
454 331
454 331
Total
1 116 412
1 116412
NET INCOME/(EXPENDITURE)
Other recognised galns/(losses)
Gains on revaluation of fixed assets
{22,104)
(22,104)
310 000
310 000
Net movement in funds
287,896
287,896
RECONCILIATION OF FUNDS
Total fuiids brought forward
1,273,223
1,273,223
TOTAL FUNDS CARRIED FORWARD
1 561 119
1 561 119
Page 28
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS- continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
14. INTANGIBLE FIXED ASSETS
Development
costs
COST
At 1st January 2024
Additions
190,108
At 31st December 2024
236 404
AMORTISATION
At 1st January 2024
Charge for year
138,960
At 31st December 2024
193 128
NET BOOK VALUE
At 31st December 2024
At 31st December 2023
15. TANGIBLE FIXED ASSETS
Fixtures
and
fittings
Freehold
property
Totals
COST
At 1st January 2024
Additions
Disposals
I,ioo,000
56,838 1,156,838
7,357
7,357
42 784)
1 142 784)
i loo 000)
At 31st December 2024
21,411
DEPRECIATION
At 1st lanuary 2024
Charge for year
Eliminated on disposal
51,560
3,928
42 784)
51,560
3,928
42 784)
At 31st December 2024
NET BOOK VALUE
At 31st December 2024
At 31st December 2023
i loo 000
1 105 278
The Institute also owns the President's Chain and Lady's Pendant which have not been
Incorporoted into the balance sheet. The Chain and Pendant are valued for insurance purposes.
Page 29
continued...

THE CHARTERED INSTrruTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - contTnued
FOR THE YEAR ENDED 31ST DECEMBER 2024
16. FIXED ASSET INVESTMENTS
Shares in
group
Listed
undertakings investments
Totals
MARKET VALUE
At 1st January 2024
Additlons
Revaluations
1,302,365
1,302,365
At 31st December 2024
1 310 248 1 310 251
NET BOOK VALUE
At 31st December 2024
1 310 248 1 310 251
At 31st December 2023
There were no Investment assets outslde the UK.
Cost or valuation at 31st December 2024 Is represented by:
Shares In
group
Listed
undertaklngs investments
Totals
Valuation in 2024
Cost
7,883
1 302 365
7,883
1 302 368
1 310 248 1 310 251
The company's Investments at the balance sheet date in the share capital of companies include the
following..
Plumblng & Heating Promotions Limited
Registered office.. Saxon House, 27 Duke Street, Chelmsford, Essex, CMI IHT
Nature of buslness: Non-trading
Class of share..
Ordlnarv
holding
loo
2024
2023
Aggregate capital and reserves
Greenplumb Limited
Registered office.. Saxon House, 27 Duke Street, Chelmsford, Essex, CMI IHT
Nature of business: Non-trading
Class of share,.
Ordinary
holding
loo
2024
2023
Aggregate capital and reserves
Page 30
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATJNG ENGINEERING
NOTES TO THE FINANCIAL StATEMENTS- contlnued
FOR THE YEAR ENDED 31ST DECEMBER 2024
16. FIXED ASSET INVEsfMENTS- contlnued
Safeplumb Limlted
Registered office: Saxon House, 27 Duke Street, Chelmsford, Essex, CMI IHT
Nature of business: Non-trading
Class of share:
Ordinary
holding
loo
2024
2023
Aggregate capital and reserves
Market value is considered to be the same as historical cost.
17. STOCKS
2024
2023
Stocks
18. DEBTORS: AMOUNTS FALLING DUE WITHIN ONE YEAR
2024
2023
Trade debtors
Other debtors
VAT
Prepayments & accrued income
19,038
6,100
4,772
21,408
loo
19. CREDITORS: AMOUNTS FALLING DUE WITHIN ONE YEAR
2024
2023
Trade creditors
Socla I security and other taxes
VAT
Other credltors
Deferred income
Accrued expenses
10,933
14,609
15,119
16,635
84
8,719
292,960
8,719
296,726
14,940
345 927
349 521
Deferred income represents 2025 membership fees received before the 31st December 2024 of
£296,726 (2023.. £292,960) are included in creditors: amounts falling due within one year.
Page 31
continued...

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
20. LEASING AGREEMENTS
Mlnlmum lease payments under non-cancellable operating leases fall due as follows..
2024
2023
Within one year
21. MOVEMENT IN FUNDS
Net
movement
In funds
Transfers
between
funds
At
31.12.24
At 1.1.24
Unrestrlcted funds
General fund
Revaluation Reserve
528,134
1 032 985
179,728
1,032,985
1 032 985)
1,740,847
1 561 119
187 611
1 748 730
TOTAL FUNDS
1 561 119
187 611
1 748 730
Net movement In funds, included in the above are as follows:
Incoming
resources
Resources
expended
Gains and
losses
Movement
in funds
Unrestrlcted funds
General fund
RevaluatSon Reserve
1,422,702 (1,242,974)
179,728
1 422 702
1 242 974)
187 611
TOTAL FUNDS
1 422 702
1 242 974)
187 611
Comparatlves for movement In funds
Nel
movement
in funds
At
31.12.23
At 1.1.23
Unrestricted funds
General fund
Revaluation Reserve
550,238
722 985
(22,104)
310 000
528,134
1 032 985
1 273 223
287 896
1 561 119
TOTAL FUNDS
1 273 223
287 896
1 561 119
Page 32

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
NOTES TO THE FINANCIAL STATEMENTS - continued
FOR THE YEAR ENDED 31ST DECEMBER 2024
21.
MOVEMENT IN FUNDS - contlnued
Comparative net movement in funds, included in the above are as follows:
Incoming
resources
Resources
expended
Gains and
losses
Movement
in funds
Unrestricted funds
General fund
Reva luation Reserve
1,094,308 (1,116,412)
(22, 104)
310 000
310 000
1 094 308
1 116 412)
310 000
287 896
TOTAL FUNDS
1 116,412)
310 000
287 896
A current year 12 months and prior year 12 months combined position is as follows:
Net
movement
in funds
Transfers
between
funds
At
31.12.24
At 1.1.23
Unrestrlcted funds
General fund
Revaluation Reserve
550,238
722 985
157,624
317 883
1,032,985
1 032 985)
1,740,847
1 273 223
475 507
1 748 730
TOTAL FUNDS
1 273 223
475 507
1 748 730
A current year 12 months and prlor year 12 months combined net movement in funds, included in
the above are as follows:
Incoming
resources
Resources
expended
Gains and
losses
Movement
in funds
Unrestricted funds
General fund
Revaluation Reserve
2,517,010 (2,359,386)
157,624
317 883
317 883
2 517 010
2 359 386)
317 883
475 507
TOTAL FUNDS
2 517 010
2 359 386)
317 883
475 507
22. RELATED PARTY DISCLOSURES
There were no related party transactions for the year ended 31st December 2024.
23. FRC ETHICAL STANDARD - PROVISIONS AVAILABLE FOR SMALL ENTITIES
In common with many other businesses of our size and nature we use our auditors to prepare and
submit returns to the tax authorities and assist with the preparation of the financial statements.
Page 33

THE CHARTERED INSTITUTE OF PLUMBING &
HEATING ENGINEERING
DETAILED STATEMENT OF FINANCIAL AcfIviTXES
FOR THE YEAR ENDED 31ST DECEMBER 2024
2024
2023
INCOME AND ENDOWMENTS
other tradlng actlvities
Sales of supplies
Offlce services
Sundry income
79,657
83,154
57,876
30,617
167,293
103,601
Investment Income
Deposlt account interest
51,168
13,875
Charltable activlties
Fee5 from members
Publlcations
948,580
940,737
984,988
976,832
other Income
Galn on sale of tanglble fixed assets
219 253
Total incoming resources
1,422,702
1,094,308
EXPENDITURE
other trading actlvltles
Cost of supplles 501d
22,925
19,864
Charltable artlvltles
Wages
Soclal securltv
Penslons
Maintaining professional standards
Magazlne costs
Awareness
Service for members
Grants to Institutions
247,698
26,338
14,768
55,618
103,046
64,363
12,317
214,197
23,378
14,135
56,755
97,128
49,763
12,633
550,144
492,137
Support costs
staff costs
Wage5
Social security
Pensions
other staff costs
205,792
16,934
13,156
224,540
15,919
12,988
270,189
260,625
Communlcatlons
Telephone
Carried forward
4,020
4,020
4,117
4,117
Page 34

THE CHARTERED INSTftUTE OF PLUMBING &
EATING ENGINEERING
DETAILED STATEMENT OF FINANCIAL ACTIVITIES
FOR THE YEAR ENDED 31ST DECEMBER 2024
2024
2023
Communlcations
Brought forward
Postage and stationery
4,020
4,117
30,822
26,642
Office costs
Insurance
Postage and statlonery
Repalrs and renewals
Sundries
IT support service5
Depreciation of tangible fixed asset5
12,892
14,194
2,332
3,468
43,893
13,229
19,961
5,057
5,800
41,350
134,875
137,383
Premlses costs
Other operating leases
Rates and water
Light and heat
Premlses repalrs
24,036
1,428
3,752
3,552
5,842
36,182
14,949
Flnance costs
Bank charges
Card servlce charges
8,828
8,402
23,009
16,072
Other
Legal & professional fees
Subscriptions
Unrecoverable VAT
10,986
5,335
29,894
3,843
5,652
46,215
32,533
Meeting & conference expenses
Meeting expenses
Website expenses
Event expenses
27,864
46,204
32,636
44,230
74,068
81,972
Governance costs
Wages
Social security
Pensions
Auditors, remuneration
Auditors, remuneration for non-audit work
36,552
3,689
2,322
10,897
17,315
3,525
2,292
10,058
Total resources expended
1 242 974
1 116 412
Net income/(expenditure)
179,728
22 104)
Page 35